Power line finish date extended

BC HYDRO has pushed back the completion date for its Northwest Transmission Line.

  • Dec. 7, 2011 5:00 p.m.

BC HYDRO has pushed back the completion date for its Northwest Transmission Line.

Instead of a completion date at the end of 2013, the 287kV power line, which will run up Hwy37 North, won’t be operational until sometime in the spring of 2014.

Speaking last week, Tim Jennings, the BC Hydro official in charge of the project, said a number of factors added up to the overall delay.

Those included an environmental review that lasted longer than expected and challenges in arranging for the start of construction with Valard/Valard and Burns & McDonnell, the crown corporation’s primary design-build contracting group.

Jennings conceded that BC Hydro may have been over optimistic when it first set out its construction and completion timetable.

“We’ve had delays, if you will, and there’s been more time spent than we had originally planned to get [environmental] approvals and other factors,” he said.

“We had really hoped to get construction started this season. But we are as committed as ever,” Jennings continued.

Negotiating impact benefits agreements with First Nations who have traditional territory along the pipeline route and with the Nisga’a Nation did not cause delays, Jennings added.

Those agreements, which provide money and job and business opportunities for First Nations, were not considered a mandatory part of the overall project.

“[Impact benefits agreements] are not tied to the schedule,” said Jennings.

Jennings did not anticipate the delay will affect the overall construction cost for the line.

BC Hydro has been unable to provide a set price, saying the project will cost between $365 million and $525 million, a range it first set out several years ago.

“We’re still within that range,” said Jennings.

But he did say that project costs have been increasing toward the upper end of the estimated range.

Jennings anticipates a start to construction by the end of December, work he defined as falling trees and clearing land leading to building roads to the actual power line route.

To date, the physical work has been marking out the route’s centre line and conducting drilling and other geotechnical work in preparation for the start of construction.

The delay will not affect work on the Forrest Kerr run-of-river hydro project belonging to AltaGas.

That project, which involves diverting water from the Iskut River and running it through turbines before returning it to the river, isn’t scheduled to be finished until July 2014 in any event.

“AltaGas has been advised of the shift in the in-service date and is working collaboratively with BC Hydro to help facilitate, and where possible, improve the [Northwest Transmission Line] schedule by sharing resources if there is an opportunity to do so,” states a Dec. 2 email from AltaGas.

The project cost of approximately $700 million won’t be affected either.

AltaGas has a 60-year contract to sell electricity to BC Hydro by transmitting it through the Northwest Transmission Line.

It is also paying BC Hydro $180 million toward the construction of the transmission line.

AltaGas also says the delay won’t affect the timing of two smaller run-of-river projects it wants to build in the region.

McLymont Creek and Volcano Creek aren’t expected to be finished until November 2015.

 

Just Posted

DFO announces openings for chinook

Opportunities are few between widespread closures

Lost Lake closed for fishing due to goldfish invasion

Pet fish is considered an invasive species to B.C. wild

Skeena Voices | Designing a strong identity

Kelly Bapty is the province’s first Indigenous female architect from a B.C. nation

Northwest couples compete at His and Hers golf tournament in Prince Rupert

Kitimat and Smithers couples take home the hardware

Feds announce funds to replace Kitimat’s Haisla River Bridge

Bill Morneau said Ottawa’s $275 million will also help fund high energy-efficient gas turbines

VIDEO: Killer whale steals fisherman’s catch off North Coast

Fishing duel results in eager orca snagging salmon in Prince Rupert

Fate of accused in Canadian couple’s 1987 killings in jury’s hands

William Talbott’s lawyer says DNA doesn’t prove murder

Child killed after being hit in driveway on Vancouver Island

The driver of the vehicle remained at the crash scene and is fully cooperating

Eating sandwiches, putting on makeup behind the wheel could land you a fine

RCMP say if you cause an accident while eating you could be penalized

Cat badly hurt in animal trap was likely stuck for days, B.C. owner says

Blu, a three-year-old house cat, suffered severe damage to his hind leg after being stuck in trap for days

40 cats surrendered in apparent hoarding at B.C. home

Officers found the cats living among piles of garbage and feces, suffering from fleas

Vancouver Aquarium drops cetacean ban lawsuit in new lease agreement

Ocean Wise CEO Lasse Gustavsson called the updated lease an exciting new chapter for the aquarium

Thieves steal two $40K chairs featuring gold serpents from B.C. furniture store

Chairs believed to be the only two of its kind in Canada, police said

Rising gas prices force B.C. residents to rethink summer road trips: poll

63 per cent of respondents reported gas prices are impacting their day-to-day finances

Most Read