Pipeline delays add appeal to creative options for Canada’s oil transport, transformation

Trans Mountain expansion and Keystone XL pipeline projects in court limbo trigger new ideas to get oil to market

News that permitting issues in the U.S. would delay Enbridge Inc.’s Line 3 replacement pipeline project until the middle of 2020 instead of late this year means that yet another boost in oil export capacity has been kicked down the road.

With both the Trans Mountain expansion and Keystone XL pipeline projects in court limbo, attention is turning to alternative ideas to expand Canada’s ability to continue to get its oil to market.

In a report to Natural Resources Minister Amarjeet Sohi last month, the National Energy Board said current pipeline capacity is fully utilized and crude-by-rail infrastructure is operating at or near capacity.

But it also identified potential long-term market access solutions that could include more oilsands bitumen upgrading and reversing existing import pipelines.

Unfortunately, none of those ideas works as a meaningful short-term alternative to new pipelines — and they face many of the same speed bumps — says NEB chief economist Jean-Denis Charlebois.

READ MORE: Canada says B.C. trying to impede Trans Mountain with pipeline legislation

READ MORE: B.C. says it won’t reject pipelines without cause

“Fundamentally, what this would require is regulatory approvals and significant capital investments because those things cannot occur overnight,” he said in an interview.

“First the economics have to be there … then those alternatives need to go through a regulatory process.”

A dearth of investment dollars for traditional drilling in Western Canada means there are also fewer dollars available for developing creative options, said Kevin Birn, a vice-president with IHS Energy in Calgary.

“I think you will have some creativity but if you really want creativity, they’ve got to see a future for investment in Western Canada,” he said.

Here’s a closer look at some pipeline alternative solutions.

The diluent dilemma

Raw bitumen at room temperature has the consistency of peanut butter. Below freezing, it’s as hard as a hockey puck.

To make it flow in a pipeline, producers mix as many as three barrels of light oil “diluent” for every seven barrels of bitumen — if one can eliminate or reduce the diluent, it frees up room in the pipeline.

In January, the Alberta government announced a $440-million loan guarantee to help Value Creation Inc. build a $2-billion upgrader that would convert diluted bitumen into medium synthetic crude and diesel, both capable of flowing undiluted in a pipeline.

The facility is the first in line for up to $1 billion in provincial incentives for partial upgraders, but it isn’t expected to be operating until at least 2022.

A report prepared for the province in 2017 suggested that a 100,000-barrel-per-day partial upgrading facility could add $10 to $15 of value to each barrel of bitumen. The report listed 10 pre-commercial technologies that have been tested or proposed for deployment in Alberta.

Any plan to reduce diluent must consider the impact on U.S. customers, who have configured their refineries to use diluted bitumen, said Birn.

He added diluent will still be needed to deliver the bitumen from the field to the partial upgrader, which means diluent recovery units likely also will need to be built.

New technology

No diluent at all would be required with a new technology to mix and coat bitumen with recycled plastic and form it into solid pucks for shipping in ordinary railcars or shipping containers.

An oil company affiliated with the tiny Heart Lake First Nation in northern Alberta is building a $50-million pilot plant to test the “CanaPux” product developed by Canadian National Railway Co.

But it’s not known when a commercial facility would follow.

Pipeline efficiency

Reducing the demand for diluent in Canada could help Enbridge decide on the option to convert its Southern Lights pipeline — used to import U.S. condensate diluent into Canada — into a crude oil export pipeline with capacity of about 150,000 bpd, possibly by 2023.

Meanwhile, the operator of the biggest oil export pipeline network in Canada is getting creative as it looks at using drag reducing agents inside the pipe and redirecting some downstream U.S. injections to open up long-haul capacity for Western Canada, along with low-cost pipeline and pumping station upgrades.

It thinks it could add another 50,000 to 100,000 bpd of incremental export space by mid-year and is studying a potential 450,000 bpd of throughput optimization initiatives.

Crude-by-rail

Rail exports rose to a record of over 350,000 bpd in December before falling in January and February after Alberta imposed production cuts to reduce storage and open up space on pipelines.

They are on the rise again as Alberta loosens its production quotas and Imperial Oil Ltd. restarts rail shipments it stopped in February.

Crude shipped by rail often contains diluent but the NEB notes more oil can be put in each car if the oil isn’t diluted — although that requires the use of cars that can be heated at the destination dock to drain the bitumen.

Meanwhile, Alberta’s NDP government is pressing ahead with plans to add locomotives and railcars to move 120,000 barrels per day of crude, starting at the end of the year — although the opposition United Conservative Party has vowed to kill the order if it wins the provincial election this week.

Dan Healing, The Canadian Press

Like us on Facebook and follow us on Twitter.

Just Posted

Terrace man killed in logging accident ‘would have done anything for anyone’

Wife remembers 43-year old Petr Koncek, father of two children

New Seven Sisters replacement confirmed

Mental health facility will have 25 beds, up from 20 in current facility

Skeena Voices | The strums of euphony

Music teacher Geoffrey Parr will be retiring after 30 years at Caledonia Secondary School

Terrace hospital’s business plan approved

Health Minister’s announcement opens door to construction phase

Killer of Calgary mother, daughter gets no parole for 50 years

A jury found Edward Downey guilty last year in the deaths of Sara Baillie, 34, and five-year-old Taliyah Marsman

Ottawa spending $24.5M to research on health benefits, risks of pot use

$390,000 will fund two cannabis public awareness

Crackdown on money laundering does not include federal public inquiry: minister

An independent report commissioned concluded $7.4 billion was laundered in B.C. last year

Trudeau’s action plan on climate change brings B.C. politician out of retirement

Terry Lake, a former B.C. health minister, is running for federal office in Kamloops-Thompson-Cariboo

Survey finds minimal progress in Canadian military’s fight against sexual misconduct

1.6 per cent of regular-force members — 900 military personnel — reported having been victims of sexual assaults over past year

Raptors beat Bucks 120-102 to even series at 2-2

Lowry pours in 25 as Toronto moves within two games of NBA Finals

Body of missing snowmobiler recovered from Great Slave Lake

Police confirm the body is that of one of three missing snowmobilers

Toddler seriously injured after falling from Okanagan balcony

RCMP are investigating after a two-year-old boy fell from the balcony of an apartment in Kelowna

Cost jumps 35% for Trans-Canada Highway widening in B.C.

Revelstoke-area stretch first awarded under new union deal

Most Read