Construction of the Trans Mountain pipeline is seen underway in Kamloops, B.C., Tuesday, Sept. 1, 2020. A new report from the parliamentary budget officer says the federal government could end up losing money on the Trans Mountain pipeline if it further tightens its climate policy. THE CANADIAN PRESS/Jonathan Hayward

Construction of the Trans Mountain pipeline is seen underway in Kamloops, B.C., Tuesday, Sept. 1, 2020. A new report from the parliamentary budget officer says the federal government could end up losing money on the Trans Mountain pipeline if it further tightens its climate policy. THE CANADIAN PRESS/Jonathan Hayward

Future value of Trans Mountain pipeline rests on Liberals’ climate plans, PBO says

The increased capacity wouldn’t come on line until the end of 2022

The federal government could end up losing money on the Trans Mountain pipeline if it further tightens its climate policy and decreasing demand for Canadian oil, the parliamentary budget officer says.

The federal government bought the pipeline, and the unfinished work to increase its capacity by twinning it, in August 2018 for $4.4 billion.

The Liberals haven’t been able to find a buyer for the pipeline from Alberta to the West Coast. They are instead paying for its expansion, which the most recent estimate says will cost $12.6 billion.

The increased capacity wouldn’t come on line until the end of 2022.

The budget officer said the pipeline remains profitable based on expected cash flows, estimating the government could make $600 million above its purchase price.

But Yves Giroux warned in his report Tuesday that everything could change based on circumstances both beyond and within the government’s control, including changes to climate policy that would reduce demand for the petroleum products the pipeline moves.

Giroux also provided a scenario for the Liberals’ promise to reach net-zero emissions by 2050, estimating that doing so could lead to a $1.5-billion loss on Trans Mountain.

And that estimate led environmental groups to argue the government should spend less on the pipeline and more on tackling climate change.

“This pipeline is only profitable in a worst-case climate scenario, where the world takes no new action on climate change,” said Keith Stewart with Greenpeace Canada. “That is not a future that we should be betting over $12 billion of public money on.”

The report Tuesday was an update on the PBO’s report from early 2019 that pegged the cost of the pipeline and planned expansion project at between $3.6 billion and $4.6 billion, meaning the government might have overpaid for the project two years ago.

READ MORE: Canada Energy Regulator projects there may be no need for Trans Mountain expansion

The Liberals have argued the costs were worth it to save a project that looked doomed when Kinder Morgan and its investors got cold feet in the face of legal opposition and political uncertainty.

Despite a series of legal wins to the pipeline’s construction, and government money going into it, a sale hasn’t happened.

It’s unlikely the Liberals will ever find a buyer because the PBO report adds to arguments that Trans Mountain isn’t economically viable, said NDP finance critic Peter Julian.

He called on the Liberals to shift spending from the pipeline to climate change projects like green energy infrastructure.

“It was a mistake for Mr. Trudeau in 24 hours to come up with ($4.4 billion) and throw that at the company,” he said during a virtual press conference.

“It would be a bigger mistake to … keep pouring money — taxpayers’ money — into this project, even though it is almost in all the scenarios that are realistic, it is going to be a money-loser.”

Giroux’s report last year estimated the government would lose upwards of $2.5 billion if the expansion didn’t go ahead.

In his report Tuesday, Giroux estimated that a one-year delay in getting the expansion online would translate into a $400 million loss. A 10 per cent drop in construction costs would put the profit margin at $1 billion, or $200 million if costs rise.

In a statement, Giroux said the precarity of the outlook lay with federal policy.

“The profitability of the assets is highly contingent on the climate policy stance of the federal government and on the future utilization rate of the pipeline,” he said.

Amara Possian, Canada campaign director for 350.org (named for a “safe” level of carbon dioxide in the atmosphere) said the PBO report makes clear the government now faces a clear choice.

“Acting on climate change and Trans Mountain don’t mix and we all need to be asking the prime minister what’s more important: saving this pipeline or tackling the climate crisis?”

Jordan Press, The Canadian Press


Like us on Facebook and follow us on Twitter.

Want to support local journalism during the pandemic? Make a donation here.

Climate changeLiberalsTrans Mountain pipeline

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

The COVID-19 outbreak at the two Coastal GasLink workforce lodges has officially been declared over. (Lakes District News file photo)
COVID-19 outbreak at Coastal GasLink worksites declared over

In total, 56 cases were associated with the outbreak in the Burns Lake and Nechako LHAs

The Nisga’a Valley Health Authority reported an isolated cluster of COVID-19 cases among non-direct care staff at the New Aiyansh Health Centre. (Gary Fiegehen/Nisga’a Lisims Government)
New Aiyansh Health Centre experiencing COVID-19 cluster among non-direct care staff

Nisga’a Valley Health Authority asking residents to cancel appointments outside the Nass Valley

A photo of the CervixCheck at-home test kit, developed by Eve Medical. (Submitted Photo/Katina Pollard, Métis Nation British Columbia)
Pilot project puts cancer screening into the hands of northwest B.C. women

Métis women experience barriers to cervical cancer screening

Brett Alexander Jones is wanted on several warrants province-wide, in connection with multiple charges. Jan. 21, 2021. Kitimat RCMP photo
Kitimat RCMP searching for man wanted on several warrants province-wide

Jones is described as a five-foot 10-inches Caucasian man, with blond hair and blue eyes.

The Nisga’a Lisims Government has extended its state of local emergency. (File photo)
Nisga’a state of local emergency extended, vaccines delayed

There are 21 active COVID-19 cases in the Nisga’a Valley Health Authority

Thursday, Jan. 28, 2021 is International Lego Day. (Jenna Hauck/ Chilliwack Progress)
Unofficial holidays: Here’s what people are celebrating for the week of Jan. 24 to 30

Lego Day, Talk Like a Grizzled Prospector Day and Puzzle Day are all coming up this week

A video posted to social media by Chilliwack resident Rob Iezzi shows a teenager getting kicked in the face after being approached by three suspects on Friday, Jan. 22, 2021. (YouTube/Rob i)
VIDEO: Security cameras capture ‘just one more assault’ near B.C. high school

Third high-school related assault captured by Chilliwack resident’s cameras since beginning of 2021

FILE - In this Feb. 14, 2017, file photo, Oklahoma State Rep. Justin Humphrey prepares to speak at the State Capitol in Oklahoma City. A mythical, ape-like creature that has captured the imagination of adventurers for decades has now become the target of Rep. Justin Humphrey. Humphrey, a Republican House member has introduced a bill that would create a Bigfoot hunting season, He says issuing a state hunting license and tag could help boost tourism. (Steve Gooch/The Oklahoman via AP, File)
Oklahoma lawmaker proposes ‘Bigfoot’ hunting season

A Republican House member has introduced a bill that would create a Bigfoot hunting season

Economic Development and Official Languages Minister Melanie Joly responds to a question in the House of Commons Monday November 23, 2020 in Ottawa. THE CANADIAN PRESS/Adrian Wyld
Federal minister touts need for new B.C. economic development agency

Last December’s federal economic update promised a stimulus package of about $100 billion this year

FILE - In this Nov. 20, 2017, file photo, Larry King attends the 45th International Emmy Awards at the New York Hilton, in New York. Former CNN talk show host King has been hospitalized with COVID-19 for more than a week, the news channel reported Saturday, Jan. 2, 2021. CNN reported the 87-year-old King contracted the coronavirus and was undergoing treatment at Cedars-Sinai Medical Center in Los Angeles. (Photo by Andy Kropa/Invision/AP, File)
Larry King, broadcasting giant for half-century, dies at 87

King conducted an estimated 50,000 on-air interviews

BC Coroners Service is currently investigating a death at Canoe Cove Marina and Boatyard in North Saanich. (Black Press Media File)
Drowning death in North Saanich likely B.C.’s first in for 2021

Investigation into suspected drowning Monday night continues

Kimberly Proctor, 18, was murdered in 2010. Her family has spent many of the years since pushing for a law in her honour, that they say would help to prevent similar tragedies. (Courtesy of Jo-Anne Landolt)
Proposed law honouring murdered B.C. teen at a standstill, lacks government support

Ministry of Mental Health and Addictions has concerns with involuntary detainment portion of act

Chief Public Health Officer Theresa Tam speaks during a daily briefing in Ottawa. (THE CANADIAN PRESS/Adrian Wyld)
31 cases of COVID-19 variants detected in Canada: Health officials

Dr. Theresa Tam made announces 13 more variant COVID-19 cases in Canada

Daily COVID-19 cases reported to each B.C. health region, to Jan. 20, 2021. Island Health in blue, Northern Health green, Interior Health orange, Vancouver Coastal in red and Fraser Health in purple. (B.C. Centre for Disease Control)
B.C.’s COVID-19 infection rate stays stable with 508 cases Friday

Vaccine delivered to more than 110,000 high-risk people

Most Read