Clark warns of $600 million delay to Site C dam

NDP leader John Horgan says Clark’s claims ‘unsupported’

Premier Christy Clark has written to the NDP and Green Party leaders, warning that a delay in removing two homes from the path of a Site C dam road could delay the project by a year and cost as much as $600 million.

In letters released Tuesday, Clark asked both NDP leader John Horgan and B.C. Green Party leader Andrew Weaver to reconsider Horgan’s request to delay the removal of two homes on land expropriated by BC Hydro for the third dam on the Peace River.

A decision must be made by June 15 on whether to proceed, Clark wrote. Her letters also ask:

“…whether or not you would like government to issue a ‘tools down’ request to BC Hydro on the other decisions that are essential in maintaining the budget and construction schedule of the Site C Clean Energy Project, given that the project is likely to progress past the ‘point of no return’ before the B.C. Utilities Commission review you have suggested could be reasonably concluded.”

Horgan responded Tuesday, calling Clark’s claims of cost escalation “unsupported” and accusing the B.C. Liberals of driving up BC Hydro bills due to “mismanagement” of the project.

Weaver also responded to Clark’s letter Tuesday, saying he would need access to official documents on the project before he could respond to her questions.

Horgan wrote to BC Hydro CEO Jessica McDonald May 31 to ask for a lease extension for two families, including Peace Valley Landowner Association members Ken and Arlene Boon, whose homes are on a road right-of-way needed for the dam.

“I believe there is no demonstrated short-term need to force these families from their homes, and because the status of the next governments of British Columbia are uncertain, the threat of imminent removal of residents from their expropriated homes and property is unreasonable,” Horgan wrote.

Clark’s letter says “the relocation of the homes in question is necessary as part of a two-year road and bridge construction project that will enable river diversion to occur in September 2019.”

River diversion has to be done when water is low in summer, not in winter when the two existing Peace River dams are running water through turbines to supply winter electricity demand.

“Preliminary work undertaken on this issue by BC Hydro indicates that should river diversion not be completed as scheduled, a year-long delay would occur in order to divert the river during the next low-flow period, in September 2020,” Clark wrote. “This one-year delay is estimated to cost ratepayers $600 million.”

“Given the obligation that BC Hydro has in place with respect to road construction and completion, a decision to proceed will need to be made no later than June 15, 2017 in order to maintain the September 2019 river diversion schedule.”

Weaver responded to Clark’s letter Tuesday, saying he would need access to official documents on the project before he could respond to her questions.

Just Posted

TDCSS to end on-campus daycare service

NWCC committed to finding licenced provider to fill space

Terrace teen honoured at Commonwealth writing competition

Ariadna Sullivan among 12,000 entrants vying for top awards

VIDEO: Researchers rely on drones to survey aftermath of B.C. wildfires

UBC researchers are using aerial drones to study the historic 2017 wildfires in the province

Rent continues to rise in Prince Rupert, drops in Terrace

A report from Canadian Mortage and Housing Corporation shows the average rent has risen by $132

Cops targeting risky behaviour, auto crime

Holiday campagaigns aim to keep roads safe, valuables protected

REPLAY: B.C. this week in video

In case you missed it, here’s a look at replay-worthy highlights from across the province this week

Family suspends search for missing Alberta couple, plane near Revelstoke

Due to bad weather, families of missing Albertan couple say they will resume in the spring

Canadian grocers make $3M per year from penny-rounding: UBC study

Ottawa announced plans in 2012 to phase out the copper coin

Sagmoen neighbours recall alleged hammer attack

Woman was screaming outside Maple Ridge townhouse in 2013

B.C. anti-hate campaigner finds Google search on his efforts redirects to porn

Text from online news article about Cran Campbell being used to link to suspect websites

‘The Last Jedi’ opens with $220M, 2nd best weekend all-time

As anticipated, the movie fell shy of the opening weekend for J.J. Abrams’ 2015 franchise reboot

2 couples tie the knot in Australia’s 1st same-sex weddings

West Australian couple Anne Sedgwick, Lyn Hawkins have been together for 40 years

B.C. concert promoter bans Nazi symbols at shows

A man was witnessed making a Nazi salute during a heavy metal show at Pub 340

Most Read